|











This article appeared
in Building magazine
on 20 March 2008
|

So much for common sense
The Law Lords are having a high old time with the Construction Act – first there was Melville Dundas, now it’s Reinwood vs
Brown. Both come down in favour of the employer, but will our
industry understand why?
“The question is what is the effect on the
money due when an extension of time is granted just before the
day the cash ought to be in the builder’s hands”
In the end the score was 8:1. Eight judges
saw this business of the withholding notice, deduction of
liquidated damages, extension of time and architect’s
certificates in favour of the employer. One saw it in favour of
the contractor. And yet I bet many a construction industry
wallah would vote the other way. Let me tell you the story.
L Brown & Sons was the builder. The project
was 59 apartments in Castlefield, Manchester. The employer was
Reinwood. The contract was JCT 98. Completion was due
18 October 2004. If late, £13,000 liquidated damages (LAD)
applied. Come 14 months after the due completion date, the works
were still not at practical completion. Not to worry; extensions
of time were granted by the architect all the way up to
14 December 2005. He then issued a “certificate of
non-completion”. That little ticket then allowed the employer to
begin deducting £13,000 a week. So, when payment certificate
number 29 was issued, the employer notified the builder that he
would deduct £13k a week. It came to £61,629. The remaining
£126,000 was then paid to the builder and all that was very
ordinary. It was paid on 20 January.
The story then lead to nine judges mulling
over our beloved Construction Act. Remember, the cash balance
was paid on 20 January – five days early. It so happened that on
23 January the architect granted an extension of time up to
10 January. Thank you, said the builder. Then he said to the
employer that the deduction of LAD came down from £61,000 to
£12,000. So, said the builder, he was therefore underpaid. In
other words, the architect’s extension of time meant that the
period for deducting LAD at £13,000 a week was very much less.
But the employer wouldn’t budge.
Within days of asking for payment of the now
wrong amount of LAD and getting refused, the builder served a
notice to terminate the contract. Next day the employer stumped
up £49,000, but still the builder said because the true amount
due had not been paid on time, there was a breach.
The question to be answered is what is the
effect on the money due when an extension of time is granted
just before the day the cash ought to be in the builder’s hands?
First, we know that the builder had requested
an extension of time and while the architect was mulling that
over, he quite properly calculated the amounts of money due in
the next interim certificate. It was dated 14 December; then
there is the period of days between payment certificate and
final date for payment. In that period the employer properly
notified an intention to withhold £61,000 LAD. But before the
final date for payment the architect, also properly, awarded an
extension of time so reducing the entitlement to LAD. And there
is the rub: when does the entitlement to the reduced LAD kick
in? The builder said straightaway, so please reflect that in the
cheque. No, no, said the employer, too late. He, the employer,
wanted to keep the amount withheld until the next time money was
due under an interim certificate.
Anyway these two parties dug in. There was a
High Court trial. The result was one, nil to the builder. But in
the Court of Appeal, it became 3:1 to the employer (I told you
about it on 13 July 2007).
The builder now got permission to come to the House of Lords.
The facts were that by the time the money was due to be paid,
the right to withhold all the money had disappeared. The House
of Lords looked at the JCT rules. The rules required a
certificate of non-completion and a withholding notice given in
time. Since that was all done as per JCT, those rules would be
applied. “Any other conclusion,” said Lord Neuberger, “would fly
in the face of commercial common sense.” My suspicion is that
the builder did apply commercial common sense to all this. And I
think the one judge out of nine who agreed with the builder also
did. The JCT document is a commercial tool for commercial people
as understood by commercial people. Wrong. It is a tool that the
court tells us is understood by commercial people.
Not the same is it?
Readers are invited to forward recent
judgments for reporting in this column (with full
acknowledgement) to: Tony Bingham, 3 Paper Buildings, Temple,
London EC4Y 7EU. DX: 37164 Biggleswade
Top
|