|

Talking yourself out of a job
Alright, love, I’ll rebuild your bungalow in
17 weeks for £130k. Agreed. What, you want a kitchen? That’s
extra. And where’s my dosh? All of it! Of course I need more
time, I can’t work in the rain, can I? I’ve been what?
!!£**@!!!*
“As for the Defective Premises Act, I bet
the builder said, 'Never heard of it'. And as for the odd flash
of temper, well, that’s life – look at Big Brother...”
The judge described the builder on this
project as intemperate. He was rude, aggressive, even
threatening towards his client. That by itself is a serious
breach of contract; serious enough for the client to describe
the contract as brought to an end. Lawyers call that a
repudiatory breach; this builder did not intend to co-operate
with his client.
Let me tell you the story. And let me say at
once that the builder sounds to me to be a competent
construction man with many years experience. His name is Mr Dale
and he is the owner and sole director of Safe Safe Homes. His
customer was Mrs Pamela Massingham. She and her husband had
bought a large detached bungalow in Rotherham and they wanted to
extend it. Mr Dale gave Mrs Massingham some advice. Don’t embark
on the £100,000 extension and refurb work. Instead, knock the
lot down and rebuild completely. He gave her a lump-sum price of
£130k and said the work would be completed in 17 weeks. Oh, and
there was no need for Mrs Massingham to use an architect or any
other professional because he was fully capable of doing
everything himself. Mrs Massingham said “done”. They drew up a
contract. There was no sign of a standard form, by the way.
Are you already beginning to draw breath,
suck teeth? A payment schedule had seven milestone payments,
starting with £60k upfront. Mrs Massingham said £30k. Mr Dale
said okay. Then there was a hiccup with the kitchen. Mrs Massingham
thought she would get a new one, and when Mr Dale said it wasn’t
included in the £130k she nearly withdrew from the negotiation
table.
Mrs Massingham got to the end of the 17 weeks
but the work was far from complete. She gave a new deadline of
one month beyond the 17 weeks. It was still incomplete then. The
grand order of the boot arrived and out went Mr Dale’s company.
I bet he was furious. I bet he had seen
contracts galore unfold like this one had. There were all sorts
of delaying events and variations … and most builders they let
them trundle on and finish in a reasonable time rather than when
they said they would. And as for some of the work not being up
to snuff, I bet the builder simply said it would all be OK in
the end. And as for claiming more cash than might be right, I
bet the builder said, it would all sort itself out. As for
fitness for purpose, I bet the builder said, “What’s that?” As
for the Defective Premises Act, I bet the builder said, “Never
heard of it”. And as for the odd flash of temper … well, that’s
life; look at Big Brother.
In his judgment, Judge Thornton took time to
explain one or two things. First: are these extras really
extras? A construction contract is subject to two overriding
principles. These are that a builder must carry out, without
additional payment, all work necessary to enable the job to be
completed, even if that work has not been defined in the
contract; and he must undertake all work needed to overcome any
obstruction or unforeseen eventuality in order to complete the
job. So, many of the “extras” were not extras at all.
Second, this contract had no extension of
time clause. So, all delays apart from those caused by the
client were to be accommodated in the 17 weeks deal. Bad weather
is just tough luck. Third, a lump sum contract does not entitle
the builder to payment until he achieves substantial completion
of the work. Demanding money earlier than that is a serious
breach.
The client was in truth entitled to see off
the builder on the last day of the 17th week. She gave him one
month extra but didn’t have to. Defective work, meaning work not
to a “reasonable standard”, is also a serious breach. Repeated
demands to be paid in excess of what is due is again a serious
breach. All that amounted to unequivocal evidence that the
builder did not intend to comply with the contract. Mrs Massingham
was entitled to send him away. She claimed the additional costs
of having the work completed by others. It cost Safe Safe Homes
£47,000. Bet he said few more rude words.
Readers are invited to forward recent
judgments for reporting in this column (with full
acknowledgement) to: Tony Bingham, 3 Paper Buildings, Temple,
London EC4Y 7EU. DX: 37164 Biggleswade
Top
|