|

JCT sleeps with the fishes
Standard forms are supposed to make things easy,
but that wasn’t exactly the builder’s experience in Reinwood vs
Brown. Maybe it’s time the whole lot were taken for a ride …
“Out go the workers. In come the form
wranglers. Standard forms gleam and pong like a dead mackerel in
the moonlight”
There, I knew it all along. JCT98 is as plain
as a judge’s pikestaff. Said the Lord Justice of Appeal: “In my
view, the machinery provided by the contract is clear and
straightforward, and produces a workable and commercial scheme.”
Two more Court of Appeal judges sitting alongside said: “I
agree.”
Trouble is, I have the feeling that if,
instead of asking three tip-top judges, you asked three tip-top
builders (or 30 or 300), they’d say: “Bugger, I can’t make head
nor tail of what these documents do, or say, or intend.”
And as much as I love to bits all the form
makers at JCT and even at NEC, we really ought to scrap the lot.
Start afresh. We might even get the new prime minister to spread
his tentacles of “change” into these over-complicated so-called
standard forms.
And yet, appeal judges find them
straightforward. I wonder if they would find plastering
complicated?
The Court of Appeal on 21 June explained a
building case called Reinwood vs L Brown & Sons.
It’s easy to understand. Brown, the builder, became peeved. It
said the employer had underpaid and it walked. Out went the
chippies, plasterers and plumbers. In came the form wranglers.
Standard forms gleam and pong like a dead mackerel on the
quayside in the moonlight. Now comes the arguing.
“The form says this.”
“No, no, the form says that.”
The folk arguing for the employer, Reinwood,
said it had not underpaid. If that was correct, the builder was
not only wrong to walk, but it would be liable for all the costs
and consequences of the employer having to get another builder
to complete the job. So, was it underpaid or not?
The amount due under JCT is what the
architect certifies. But according to JCT, the amount due isn’t
necessarily the amount payable. Did I hear a groan? The reason
is that the employer can deduct liquidated damages from the
architect’s certified sum if the contractor has failed to
complete the works by the date for completion.
This was what the so-called underpayment was
all about. Reinwood deducted £62k in liquidated damages; Brown
argued that the true figure was £12k. The High Court judge said
Brown was right. The three judges in the Court of Appeal said it
was wrong, and they painstakingly explained how obvious it was.
Three ingredients are necessary to deduct
liquidated damages. First, the architect must issue a
certificate of non-completion. It had. Second, the employer must
inform the contractor in writing of its intention to require
payment of liquidated damages. It did. Third it must issue the
withholding notice not later than five days before the “final
date for payment”. This was done.
Then the cheque was posted with a £62k
deduction to account for the completion of the block of flats
five weeks late.
But then the wheels came off. Just before the
cheque was due, the architect quite properly wiggled the
extension of time machinery in JCT and awarded another four
weeks. So, instead of five weeks’ liquidated damages, it was now
only one. Can you see why the builder complained about being
underpaid? And can you see why the first judge agreed? I bet all
construction folk see the force of that. I nearly called it
common sense. And it is right – except for a “but”.
The but crops up when you ask this question:
what’s the score when the three ingredients are carried out but
the architect trumps its certificate of non-completion by later
awarding an extension of time?
The Court of Appeal said once the three
ingredients were in place, particularly the employer’s
withholding notice, the system had “crystallised” the right to
rely on those pieces of paper.
The £62k deduction was not an underpayment
and the builder had no room for complaint – technically. On the
final date for payment, the cheque was right. Mind you, it does
seem that the employer was bound to repay all but £12k of the
£62k deduction.
I have not one jot of criticism of the Court
of Appeal. Down here, though, we only see things as builders,
plasterers, plumbers and High Court judges. Don’t you think
builders’ forms ought to be written so that builders can
understand them?
Readers are invited to forward recent
judgments for reporting in this column (with full
acknowledgement) to: Tony Bingham, 3 Paper Buildings, Temple,
London EC4Y 7EU. DX: 37164 Biggleswade
Top
|