|

Wriggle room
A developer tried three arguments to get round an
adjudicator’s order to pay its contractor £170k. This is what the
court said about them
“It is a wringing of hands occasion to read
an adjudicator’s decision and to have a view jump out from the
page”
Park Lane Estates was determined not to pay its
design-and-build contractor’s interim application for payment.
Snag was, the JCT’s With Contractors Design form says an employer
has to follow a certain rigmarole before it declines payment. So
when no cheque turned up, the contractor, Palmac, got an
adjudicator in.
He did his stuff and declared that £170k should
be paid. Park Lane refused. So Palmac went to the Technology and
Construction Court for enforcement. It got it, but more rigmarole
was mulled over. It was interesting stuff.
The first argument was digital. The contractor
had sent payment application number 20 by email. Park Lane said
service by email was not valid. If that is right, then no
application was made: the email is a nothing, and you can’t have a
dispute over nothing – and if you haven’t got a dispute, you can’t
have an adjudication, and the £170k isn’t enforceable. And if you
recite all that at a gallop, you might get away with it.
The adjudicator rejected that argument, and was
within his rights to do so. If he was wrong, it did not mean he
had no authority to decide that item. He did, and it is binding.
In any case, the JCT document allows “any effective means” for
communication, and if you publish your email address that invites
emails.
The second argument was about non-compliance
with the adjudication procedure that was set out in the contract.
The notice of adjudication was served through Park Lane’s
letterbox and then Palmac says it applied to the appointing body
for the adjudicator. Park Lane said it didn’t receive the notice
until the next day. Now then, a clash of evidence leads to
cross-examination. If that is necessary, enforcement proceedings
are likely to be stopped and a trial of fact ordered. But in this
case a smidgen of law was applied instead. It was decided that the
JCT WCD rigmarole does not stipulate that the nomination of the
adjudicator must only be made after service of the notice of
adjudication. Nor, by the way, is the Construction Act
prescriptive as to the timing of any nomination. The only
obligation is to “aim to secure appointment of the adjudicator
within seven days of the notice of adjudication.”
Not long ago I told you about
IDE
Contracting vs RG Carter Cambridge (13 February 2004).
There the court refused to enforce because the adjudicator was
appointed before the notice of adjudication was served. So the
adjudication was void. The rules in that IDE case were not JCT;
they were the Scheme for Construction Contracts. The previous case
was therefore of no help. But it is food for thought that if the
Construction Act is not prescriptive as to the timing of any
nomination, its offspring, the Scheme, being a statutory
instrument, is prescriptive. Odd that so much money can be wasted
as the result of such a skinny technical faux pas. Perhaps the DTI
will look at that in its review.
There is a useful comment in the judgment about
some foggy words in the JCT rigmarole. It says: “Any failure by
either party to comply with any provision in, or requirement
under, the adjudication rules shall not invalidate the decision of
the adjudicator.” These words, said the judge, are not enough to
validate the appointment of an adjudicator invalidly appointed:
its scope is limited to procedural steps within a validly
constituted adjudication.
The final point is a tricky area. The
adjudicator was accused of being unfair. It is all to do with
“taking the initiative in ascertaining the facts and the law”. The
adjudicator wrote to the parties asking for evidence about
previous interim payment applications. Both complied. When the
formal decision was made, the adjudicator expressed a view about
Park Lane’s contentions.
Its lawyers were upset that they were not able
to comment on the adjudicator’s formed view of the evidence before
he made his binding decision. It is an exasperating experience to
find that a decision was made on grounds that you were not aware
of, and so could not influence. On this occasion, however, the
adjudicator was expressing his view on the evidence adduced. The
court said that was okay. He had not committed the sin of
obtaining information from other sources and keeping it to
himself. He had not brought in new material of his own. He had
made no investigation of his own. None of this could point up
unfairness.
The truth is that once or twice, a tribunal
does not seem to have decided the case on the evidence put; even
judges have felt that draught. Taking the initiative to ascertain
the facts and the law can easily be misunderstood as constructing
one party’s case for him, even unwittingly.
Readers are invited to forward recent judgments
for reporting in this column (with full acknowledgement) to: Tony
Bingham, 3 Paper Buildings, Temple, London EC4Y 7EU. DX: 37164
Biggleswade.
Top
|