|











This article appeared
in Building magazine
on 28 May 2004
|

Step right in
By not taking extra time to decide the case, an
adjudicator led the parties straight to the courtroom door - where
they were greeted by a welcoming judge
“The adjudicator awarded £1.8m to the
claimant. But the judge would not enforce it: he said the
procedure went wrong”
The judge in
AWG
Construction Services Ltd vs Rockingham Motor Speedway Ltd
has turned the sign around on the court door. You know the one I
mean: one side says "Hello, come in, open", the other side says,
"Go away and sort your disputes somewhere else". He is open
for business. Snag is there's an awfully good competitor down the
road called Adjudications R Us, so he's had a bit of a prod at
that.
Fair dues, though: the judge admitted that six
years ago, the courts were in a mess. "There were", he said,
"significant delays in the courts". Er, hmmm that's putting
it mildly. Lord Bingham, who was at the time the most senior
judge in the civil courts, put it a fraction more seriously.
He described the expense of litigation as "a cancer eating at the
heart of the administration of justice!. On top of that the
lord chief justice, Lord Woolf, said that a number of business
people had told him that it was often cheaper to pay up
irrespective of the merits of a case rather than to defend the
action in the courts. Well, if all that is behind us, let's
get stuck in to a bit of juicy legislation.
AWG and Rockingham got adjudicating, but it
went wrong. So did 10 or so other adjudications last year.
That's about 10 out of 2000. Rockingham is that new motor
speedway track in Northamptonshire. AWG, formerly Morrison
Construction, was the design-and-build contractor for the
racetracks and grandstand, underpasses and tunnels.
Something caused seepage of water through the track surface.
There was disruption at the first race meeting and Rockingham
obtained £123,000 in an adjudication. Later, AWG claimed
£400,000 in a second adjudication and won that. Rockingham
refused to pay. Come 1 October last, Rockingham began a
third adjudication. It is that one that is the subject of
the recent judgment. The adjudicator awarded £1.8m pounds to
the claimant. But the judge would not enforce that decision;
he said the procedure went wrong. It became technically
unfair, in the eyes of the judge.
Here's what happened. Rockingham made the
statement of claim. In reply, AWG said the statement
contained new arguments and so was difficult to reply to.
Rockingham said its referral did not contain new material or
new arguments at all. By now, of course, damn near half of
the 28-day timetable had slipped by. So AWG served its
response of 147 pages under protest.
What a pity that the matter wasn't put on hold
to allow time to consider the alleged fresh stuff in the referral.
By doing that, the respondent would have had no complaints.
Hindsight! Then there was a Rockingham reply to the
response. Then one of the expert witnesses wrote a
"commentary". Then AWG complained about more new stuff while
sending in an 87-page response to the reply to the response.
Then Rockingham put in an 86-page reply to the response to the
reply to the response (phew, are you keeping up?). Then
there was another commentary by the expert and 90 pages of
evidence. Then there was an 11-page response by AWG.
Then the poor old adjudicator had four days to come up with
a decision. And he did. He awarded £1.8m to
Rockingham.
I don't think the judge was pulling anyone's
leg when he said: "I must start with an expression of admiration
that he [the adjudicator] was able to produce such a reasoned
decision of 30 pages in what was in effect three related but
separate disputed adjudications in such a short time." The
analysis of the toing and froing found that Rockingham had
"widened the issues" and turned it into a different dispute.
And by adopting new matters and new claims, which AWG did not have
enough time to respond to, that was unfair on AWG. The cynic
might suggest the adjudicator simply could not reach a sound
decision in the few days he had left.
I don't think there's a problem with
adjudicators allowing further submissions - actually, I think
that's a good thing - but they must not allow them to take away
"their" 21 days. The adjudicator should try to persuade
these folk to adopt a new timetable on an "or else" basis.
Give directions to that effect Mr. Adjudicator. And, if
someone refuses to play ball by consent, he might end up having to
litigate instead.
Readers are invited to forward recent judgments
for reporting in this column (with full acknowledgement) to: Tony
Bingham, 3 Paper Buildings, Temple, London EC4Y 7EU. DX: 37164
Biggleswade
Top
|