|

Hold up!
The adjudicator thought he had spotted an ambush.
But by heading the highwaymen off at the pass, he robbed them of
their chance to defend themselves
“The reverse ambush is unfair. Look – the
adjudication, once under way, isn’t the place to find out what’s
bugging the other bloke”
Buxton
Building Contractors Ltd vs Governors of Durand Primary School
is an adjudication case with two interesting points. The second is
what some of us call the "phantom certificate". That's the
apparition headed "interim payment" somewhere between the date of
practical completion and (the yet to come) final certificate.
"Phantom" because the JCT type contract doesn't provide for any
such interim payment certificate. Happens a lot, but its not a
contractual provision. I'll explain later.
First, let's deal with the "reverse ambush" in
adjudication. Look, an ambush by either party in a dispute is not
on. The scam is to keep hidden all, or most, or even some, of your
arguments, troops, cavalry, then pounce on the opposition at the
last minute. The "full frontal ambush" in adjudication is secretly
to prepare the umpteen lever-arch files, then call for the
adjudicator. Flummoxed, the other side won't know foot from
horseback. Adjudicators are watching for this.
The "reverse ambush" is similar stuff. This
time though the defendant has kept his powder dry. He waits until
the adjudication machine whirrs and only then presents his
arguments in the response documents. Look – the adjudication, once
under way, isn't the place to find out what is bugging the other
bloke. The agenda for adjudication isn't set during the 28 days;
it is actually set prior to the adjudication. The reverse ambush
is unfair. The ambush arguments may well be thrown out.
Buxton started the adjudication against the
employer – Durand School governors. It said in the formal
adjudication notice it required payment on an interim certificate.
But the school's response document came in with a claim in
damages. Buxton shouted foul and invited the adjudicator to ignore
these documents. He did. He then pressed on and found in favour of
Buxton. The school refused to pay up. So Buxton went to the High
Court.
The court was uncomfortable about enforcing the
otherwise binding decision. The Notice of Adjudication was wide
enough to let in the damages claim of the employer. My suspicion
is that the adjudicator thought the claim by the school in damages
was a reverse ambush. And, if he were right it would have been
unfair to let all that defence in. If it looked, for all the
world, like a brand new set of key points not previously
canvassed, then my guess is that for 10 green adjudicators sitting
on the adjudicators' wall, all 10 would have booted out the ambush
material. But Durand School plainly convinced the judge that it
had raised all their complaints with the builder well before the
adjudication got going. If that is right, then it was unfair not
to let it in as the defence. In fact, it was Buxton that acted
wrongly by only referring its side of the whole dispute. Mind you,
it would have been easy for the school to start its own
adjudication on the damages claim.
Now, what of the second point, the issue of a
certificate, marked "interim"? It was extracontractual. The JCT
Intermediate Form doesn't provide for any of this. But the
employer doesn't seem to have cared much at the time. In which
case, when does the instalment become payable for non-contractual
certificates? The Scheme for Construction Contracts will apply
when a construction contract fails to agree the intervals for a
payment deemed due. It says 17 days from the date the payment
becomes due, the certificate date is the due date. This is a neat
example of the Construction Act filling the gap in a commercial
contract in a sound way.
The employer argued in the adjudication that it
was entitled to withhold its claim for repairs from that
certificate and had issued the important Notice to Withhold before
the certificate came on the scene. There is even a hint that the
contract administrator agreed with the employer to issue the extra
contractual payment certificate and advised the employer to serve
a withholding notice. But all that fell apart when the adjudicator
was persuaded to ignore those parts of the defence. He thought he
was being scrupulously fair, and in the heat of the 28-day battle
you can't do better than that … even when wrong.
Readers are invited to forward recent judgments
for reporting in this column (with full acknowledgement) to: Tony
Bingham, 3 Paper Buildings, Temple, London EC4Y 7EU. DX: 37164
Biggleswade
Top
|