|

Ah-ha!!!
There we were thinking that adjudication was an
ambush-free zone, and then the High Court finds in favour of an
ambusher and a Christmas ambusher at that!
Is it fair that a company stands another out of
substantial sums simply because some in the industry do not work
over the Christmas period?
When a Judge says of a building dispute "I have
found this case difficult," it is worth reading. Let me tell you
the story. What do you make of it? I confess I don't like the
result. I suspect the judge didn't either. The reason I don't like
the result has nothing to do with whether it is right or wrong; it
is because it makes adjudication a breeding ground for ambushers.
And I think ambushers should be chucked out.
Here is what happened. In Orange EBS Ltd vs
ABB Ltd (22 May 2003), Orange took on the mechanical services
sub-subcontract for ABB at the trauma centre at the John Radcliffe
Infirmary in Oxford. In May 2002, Orange withdrew from site. So
ABB employed someone else and threatened Orange with the bill.
That was a repudiatory breach.
The usual correspondence was exchanged. Then it
cooled down. Six months later, in time for Christmas, Orange sent
ABB its final account. That was 2 December 2002. The account
included claims against ABB for wrongfully terminating the
sub-subcontract. The rib-tickler in adjudication goes like this:
"When is the best time to begin an adjudication?" Answer: "Just
before the whole industry shuts down for Christmas and the new
year."
Orange didn't do that. Instead, having
submitted the account on 2 December, it gave notice of
adjudication on the same day. But of course you cannot come to
adjudication unless a dispute has crystallised. ABB protested
about this previously unseen claim. The appointed adjudicator
resigned, saying he could not deal with a mere claim. ABB now said
to Orange: "Give us until 20 January to get our head around this
lot and either we agree or we agree to differ." ABB put a
consultant on the account. On 6 January, Orange called in a second
adjudicator. I bet ABB was fuming. The second adjudicator just got
on with it. Perhaps he doesn't knock off for Christmas and the new
year.
ABB said it would play adjudications but
maintained at the same time that the whole processes was wasteful
and void. The adjudicator decided that Orange had been wrongfully
dismissed and was entitled to damages and other payments. He
ordered ABB to pay a lump of money. ABB said no. Orange trotted
off to court.
Now then, we have had a string of cases in the
High Court questioning the nature of disputes. The question in
this case is whether Orange had actually referred a dispute or
not. The test for whether a dispute has arisen is neat and tidy:
"Has the process of discussion or negotiation ended and is there
now something to be decided?" That's fine. The analysis now turns
on the facts. If I send you a claim for loss and expense and you
tell me to go to blazes, that is a dispute. If you ignore me, that
too is a dispute. If you want time to consider, you are entitled
to a reasonable time. What is a reasonable time? That is a matter
of opinion.
And my guess is that the judge in Orange found
this a tight call. Counsel for ABB argued that since the industry
shuts down over Christmas and the new year, it was unreasonable
and absurd to conclude that the final account could have been
answered by 6 January. It was easy for the judge to decide that
the second adjudicator was quite right to press on with the
question of whether ABB wrongly barred Orange from the site. All
that had been well rehearsed in the correspondence. But the
account served six months later was more difficult. The
intervening holiday period was a practicality that companies must
deal with, said the judge. On the other hand, is it fair that one
company prevents another from obtaining substantial sums simply
because some in the industry do not work over the Christmas
period? Then again Orange waited six months before putting up its
account and case. Not without difficulty, the judge gave the
benefit of the doubt to Orange. The nagging doubt for me is
whether going ahead with the adjudication on 6 January rather than
20 January made the adjudication unfair. And if a dispute arises
about whether a dispute has arisen, get another adjudicator to
decide that single point. Easy. It can be done in hours and will
tell the first adjudicator where they stand.
Readers are invited to forward recent judgments
for reporting in this column (with full acknowledgement) to: Tony
Bingham, 3 Paper Buildings, Temple, London EC4Y 7EU. DX:007I LDE
Top
|