|

More cherry, anyone?
If you take a dispute to adjudication and lose, can
you go for a second bite? The answer is that you can't adjudicate
a dispute twice – except when you can …
"Put shortly, a dispute about the final
account for loss and expense is a different dispute than that
under an interim account. But be careful …"
Skanska shouted foul at this one. Landscaping
specialist ERDC Group, having had one adjudication on a dispute,
decided to have another go. The case is
Number 124 in our
enforcement series: Skanska Construction UK Ltd vs The ERDC
Group Ltd and John Hunter. I will tell you who John Hunter is
in a moment.
About 12 months ago ERDC was at odds with main
contractor Skanska over interim account number seven. The
specialist included in it a claim for prolonged stay on site, for
significant disruption and additional supervision, for head office
expenditure, financing charges, loss of opportunity and the cost
of making the claim.
That little lot came to £390,000.
There was no dispute about the measured works,
it was just a row about "extension of time" and "disruption". ERDC
got nowhere with its claim, so it called for an adjudicator.
Skanska paid up £129k and said not a penny more. The adjudicator,
Mr Fiddes, agreed with that. His decision was peppered with
frequent references to "insufficient information", "insufficient
evidence" and so on. ERDC was short on proof.
Nine months went by and ERDC came back for
another bite. Presumably it had lined up its ducks properly this
time. The prolongation and extension of time claim was pretty well
the same figure; so, too, the disruption and additional
supervision figures; the finance charges were identical; the head
office costs a tad lower.
Skanska said this was a rerun of the story and
was as unimpressed as it had been the first time. ERDC again
called for the adjudicator. John Hunter was appointed this time.
Skanska said Mr Hunter had no right to adjudicate because the
previous referee had already decided the dispute. It was what I
call a "threshold jurisdiction" challenge. Mr Hunter was invited
to pack his bags and skedaddle.
Pause here for a moment. It was gratifying to
see that Mr Hunter took the challenge to his right to adjudicate
seriously. He made a proper investigation. Some adjudicators are
inclined to be offhand about such challenges, which they suspect
to be a sham or try-on to delay things. Not necessarily so;
indeed, it might be better to stop the adjudication unless the
challenge is obviously half-baked. The waste of resources is
considerable if it is ultimately declared in court that the
adjudication was void. Mr Hunter wrote a reasoned decision as to
why he rejected Skanska's cry of foul.
Six days later Skanska was in court seeking a
declaration that Mr Hunter had no right to proceed. The Scottish
judge, Lady Paton, said Mr Hunter's analysis was sound. He had a
right to adjudicate. It was not a rerun of the earlier game.
You might be surprised by that decision: after
all, the loss and expense claim on both occasions was identical in
substance if not in all its details. My guess is that the second
adjudication was probably a second bite at the same cherry. But,
and this is the big difference, the loss and expense claim this
time was flying under the flag of the final account. Mr Hunter
and the learned judge were impressed with the argument that an
account presented as an interim account was subject to quite
different rules than one presented as the final account. The
contract in operation was DOM 1, and it has different machinery
for the two types of account.
Moreover, said the judge, the final account is
at a stage in the contract when considerably more information may
be available to the claimant and "different considerations and
perspectives may apply". Put shortly, a dispute about the final
account for loss and expense is a different dispute than that
under an interim account.
That's probably right, but you should still be
careful. It is too sweeping to say that you can simply come again
under the final account. There may well be discrete issues already
adjudicated during the course of the works, which cannot be
readjudicated. A specific decision about delay, time, money,
variations is quite different to a decision about the amount due
under an interim account in broad terms. An interim account is a
flag of convenience, not a device for rehearsing the adjudication.
Readers are invited to forward recent judgments
for reporting in this column (with full acknowledgement) to: Tony
Bingham, 3 Paper Buildings, Temple, London EC4Y 7EU. DX:007I LDE
Top
|