One way to look at it

A firm working for Alfred McAlpine put a whole load of different disputes in one basket and presented it to an adjudicator … What happened next?

"John Redmond suggests that if an adjudicator puts a sum of money into an interim account for a variation, it is not a decision about the variation"

Here is a little quiz for you. How many disputes are there in this letter between Chamberlain Carpentry & Joinery and Alfred McAlpine Construction? The letter is a “notice of intention to adjudicate” from Chamberlain, and it relies on the adjudication rules in McAlpine’s own subcontracts. The question about number is important because McAlpine says its rules, like the Scheme for Construction Contracts, only allow one dispute per adjudication. Assume that to be the correct interpretation.

Chamberlain’s notice says: “A dispute arises under the subcontract as to the following matters.” It then gave a long list of complaints. It asked for money to cover the wrongful deduction of amounts included for acceleration of the works, the wrongful deduction of amounts included for preliminaries, the wrongful deduction of the alleged duplication of measured works … and so on, all the way to prolongation costs and what it was paid for its “security worm bolts”.

McAlpine’s response, by contrast, was simple. It said “shoo” to the adjudicator: “You have no business on this pitch because this is not a dispute, it is umpteen disputes; look at all the separate complaints in the letter.” McAlpine said that the adjudication rules were broken so the notice of adjudication was invalid.

Now then, if you were the adjudicator, what would you do? There you are, all puffed up as the referee, with one team telling you to give up the job and the other telling you to press on … This adjudicator stood firm. He said it was one dispute so he would not shoo. Twenty-eight days later, he awarded Chamberlain £56k to be paid forthwith. McAlpine said that since the referee never had a right to be on the pitch, his award didn’t count and it wouldn’t pay. And do you know that if it were right about the number of disputes, it was right to give short shrift to the award? Chamberlain called on the court for help.

The judge’s job was to decide how many disputes had been sent to the referee. He started by looking at the “notice of intention to adjudicate”. That is the first round fired in any adjudication. It is supposed to give the nature of dispute, details of where and when it arose and the nature of the redress sought. The judge could also have looked at the second round fired: the “referral”. That is, the bundle of documents that present the dispute – in other words, who said what to whom. But the judge said he would only look at the notice.

He said that it was up to the party that began the adjudication to describe the dispute as it wished. What it amounted to was then to be considered objectively. The assortment of items in the notice was to be put into a matrix of fact so that a “reasonable” person could ascertain its meaning against that background. A natural and ordinary approach to a commercial contract is to apply “business” common sense. I suppose that he is asking what the parties involved meant by the words and phrases used. He looked at the “redress” called for by Chamberlain, which was “a decision as to the amount owing and due to us of the amounts wrongfully withheld”.

Oh well, said the judge, the assorted list is merely one firm asking another for a sum of money having regard to the particular matters in the notice. It was one dispute. He enforced the adjudicator’s award.

So, if this is just one dispute, what is the status of each decision taken by the adjudicator on the way to the overall decision? For example, if he allows something for the prolongation claim in the list, is that a binding decision on that bit of the dispute? Or are these “bit part” decisions merely matters “taken into account” when making the big one? Can we still bring the dispute about the prolongation to a subsequent adjudication? Or has it already been adjudicated upon? John Redmond’s book Adjudication in Construction Contracts suggests that if an adjudicator puts a sum of money into an interim account for a variation that is being quarrelled over, it is not a decision about the variation. That matter can still come as an adjudication. This may be right. Interim valuations by the employer’s QS often include a sum of money “on account” of a quarrel yet to be sorted. This is best understood by thinking of the adjudicator as a certifier with judicial overtones. In other words he can “take into account” such matters as he sees fit to give an interim certificate/decision/award, call it what you like. So, if McAlpine wants to pick a fight with Chamberlain about one of the bit parts, the door may be open – may.

Readers are invited to forward recent judgments for reporting in this column (with full acknowledgement) to: Tony Bingham, 3 Paper Buildings, Temple, London EC4Y 7EU. DX:007I LDE

Top Top


This website is designed and maintained by Web Designers
©   A. W. Bingham, 2002.  All rights reserved.