|

Question a silly answer
An adjudicator makes a boob and the judge says he
has answered the wrong question. But he hasn't: he's just answered
the right question wrongly
"On the path to the ultimate answer, the adjudicator has to answer important sub-questions. Each is a potential error"
Thank goodness that C&B Scene Concept
Design Limited vs Isobars – number
71 in our adjudication enforcement series – was not case
number one. It is, how shall we say … not quite on all fours
with the guidance given to the industry in previous cases. The
judge would not oblige Isobars to obey the adjudicator's decision
on the grounds of "excessive assumption of
jurisdiction".
Put another way, the judge didn't agree with
the adjudicator's interpretation of the contract, which was the
basis of his decision. It was rather like asking Patrick the way
to Kilkenny and him saying: "Well, I wouldn't start from
here." The judge didn't like where the adjudicator started;
he was now on the wrong road and "addressing himself to the
wrong task", hence the "excessive assumption of
jurisdiction".
Let me tell you the story. C&B Scene
Concept Design had developed a unique cafe-bar for roll-out
throughout England. Isobars engaged C&B to build the concept.
The contract was JCT with Contractors' Design 1998. That document
gives a choice for payment machinery. Guess what: they didn't
choose. The Scheme for Construction Contracts filled the gap. The
judge and the adjudicator are at one here. But now they part
company.
This particular contract contains a special
rule. I don't know of any other contracts that say this. It is
that if the contractor sends in his interim claim it becomes
"the amount due" if and only if the employer fails to
reply with a different figure. By the way, some adjudicators have
thought that this rule applied in loads of other contracts. It
doesn't. Anyway, the adjudicator decided that since the employer
had not raised a quarrel with C&B's interim application, it
should be paid. Oh no, said the judge, all that falls away; that
rule can't apply when the scheme is imported.
Hold on a moment. Let's doff our cap to the
judge. Assume he is right. The 70 previous cases in this column
have repeatedly told us that adjudicators' decisions, even if
wrong, are binding until the case goes to arbitration or
litigation. The only exception is if an adjudicator makes a
decision on something outside their jurisdiction; then they can be
challenged. Adjudicators have to mind their own business.
But, let me put this next bit gently: judges
also have to mind their own business. The court can't revise or
review an adjudicator's decision on the grounds of errors of fact
or law. And if that is right, the adjudicator's decision as to the
status of the contractors application for payment and whether it
is payable is binding whether right or wrong. If he wrongly
interpreted the contract, he hasn't answered the wrong question
and gone outside his jurisdiction; he has answered the question
wrongly.
In C&B Scene, the key issue of substance
was whether or not an invoice was payable. That is the ultimate
question. But when travelling the path to the ultimate answer, the
adjudicator always has to answer important sub-questions on the
way. Each is a fork in the road. Each fork is a potential error.
But the answers are solely for the poor old adjudicator. No court
has jurisdiction to investigate the trail, the forks, the route,
then choose different answers.
Bouygues UK Limited vs Dahl-Jensen, case 12,
offered the following guidance: "Where the adjudicator has
gone outside his terms of reference, the court will not enforce
his purported decision. This is not because it is unjust to
enforce such a decision. It is because such decision is of no
effect in law. In deciding whether a decision has been made
outside an adjudicator's terms of reference, the court should give
a fair, natural and sensible interpretation to the decision in the
light of the disputes that are the subject of the reference.
"There will be some cases where it is
clear that the adjudicator has decided an issue that was not
referred to him or her. But in deciding whether the adjudicator
has decided the wrong question rather than given a wrong answer to
the right question, the court should bear in mind that the speedy
nature of the adjudication process means that mistakes do occur,
and it should guard against characterising a mistaken answer …
as an excess of jurisdiction."
Readers are invited to forward recent judgments for reporting
in this column (with full acknowledgement) to: Tony Bingham,
3 Paper Buildings, Temple, London EC4Y 7EU.
DX:007I LDE
Top
|