|

Nothing by halves
If an adjudicator fails to take into account part
of your defence, can you get their decision overturned? Frogmore
Investments found out...
"The referring party cannot beat the system by referring only half the dispute. It must come with the whole dispute"
Answer this: If an Adjudicator makes a mistake
and decides something that they weren't asked to, does the
decision have any effect? The answer, according to the High Court,
is that the decision on that part is of no effect. That was
explained to us ages ago.
Now answer this: If an adjudicator makes a
mistake by failing to deal with a matter that has been squarely
placed before them, is that decision likewise of no effect? This
is what was examined in case number 59 of our adjudication
series,
Farebrother Building Services Ltd vs Frogmore Investments Ltd.
Now then, be careful with this judgment. The
contract was governed by the TECSA Adjudication Rules 1999,
published by the Technology & Construction Solicitors
Association. What follows therefore may not have general
application, or be made to apply to "the scheme" rules.
This is the story. Farebrother argued with
Frogmore about extensions of time. The contractor said it was
entitled to 22 weeks and the consequent expense, together with
disruption costs that ran to £900,000. Frogmore rejected that
claim. So then the claim became a "dispute". Farebrother
decided to call for an adjudicator. He was Peter Curtis.
Frogmore's defence was that it could defeat the
22 weeks claim and persuade the adjudicator that the contractor
was in culpable delay. This meant it ought to be paid £300,000
damages for late completion. It's an ordinary story, but serious
numbers were involved.
The contractor now complained that this defence
was outside the scope of the dispute referred, and therefore
Curtis had no jurisdiction to deal with it. I think the contractor
was saying that it was a surprise defence. Curtis took counsel's
opinion, thought carefully about the advice and announced that he
had no jurisdiction to deal with the counterclaim. He then pressed
on with the extensions of time argument.
In due course his opinion was published. He
said the contractor was entitled to 22 weeks extension, together
with £600,000 for prolongation and disruption. Frogmore wouldn't
pay. So Farebrother went to court. Frogmore told the court that
since the adjudicator had failed to deal with its defence, the
court should not enforce.
It was, said counsel, a matter that went to
jurisdiction. The judge thought it was more a matter that went to
the conduct of the adjudication. And if it was an error of
conduct, the decision would nevertheless be binding. This is
especially so under the TECSA rules. They allow the adjudicator to
decide what other matters must be included, beyond the
"notice of intention to adjudicate", to make the
adjudication meaningful. If Curtis thought the defence was frozen
out, it was out. So the published opinion of the adjudicator was
not to be interfered with by the court; it was summarily
enforceable.
At the heart of adjudication is the simple idea
that you must come to the table with something called a fully
developed "dispute". That means that you include all the
arguments canvassed in the toing and froing of pre-adjudication.
The file closes when the notice of intention to adjudicate is
given. The dispute is frozen, some say crystallised, at that
point. If a responding party comes galloping along during the
adjudication with a surprise defence, the adjudicator is likely to
reject that contribution. If they didn't, the whole affair might
turn into a different dispute.
But the referring party cannot beat the system
by referring only half the dispute. It must come with the whole
dispute and nothing but the dispute. It was open to Frogmore, I
suppose, to argue that Farebrother knew all its arguments about
the £300,000 counterblast, and that Farebrother had not referred
the whole dispute. If the adjudicator had agreed, the adjudication
would have stopped there and then.
The duty of the referring party is to refer the
whole dispute, including the other side's position. As for any
responding party thinking of springing a surprise defence, think
on – you might be frozen out.
Readers are invited to forward recent judgments for reporting
in this column (with full acknowledgement) to: Tony Bingham,
3 Paper Buildings, Temple, London EC4Y 7EU.
DX:007I LDE
Top
|