|

Ask yourself this
How would you feel if an adjudicator decided your
case on a question you didn't ask her, without giving you a chance
to put your views on it? And do you think a judge would agree with
you?
"She took the issue into the conference hall of her own mind and relied on her one-woman debate. Karl was not happy"
Karl Construction (Scotland) was determined not to comply with
adjudicator Janey Milligan's decision that £39 872.24 should be
paid to Sweeney Civil Engineering. It said she had answered a
question not put to her and which, therefore, did not fall within
her jurisdiction. More than that, it reckoned that the adjudicator
had thought of the question herself, had mulled over the question
herself, had not told either party she was asking and answering
the question and, above all, had not given the parties an
opportunity to have their say. Assume, please, that Karl is right.
Now answer this: will a court nevertheless enforce the
adjudicator's decision? And will you put your last 10 shillings on
that answer?
Let's deal with each of these two points, one at a time. The
first is whether a question or contention that is not mentioned in
the adjudication notice or referral documentation is nevertheless
"in scope". The answer is "sometimes". The
pathway to a decision about a dispute will meet numerous dilemmas.
They are forks in the pathway. Each will be a sub-issue or
contention that has to be answered before moving on. In Sweeney's
case, it had a dispute about money payable in an interim account.
Karl said the money wasn't due yet. Ordinary stuff. Yet the path
will be strewn with umpteen questions. The adjudicator will have
to make a finding, explaining why she was not going along one or
other of the paths suggested to her by the parties. Moreover, the
adjudicator will invariably think of questions herself. Indeed,
the whole idea of adjudication is to use an independent outsider
who knows the business of construction so well that he or she
knows what to look for. But she would be wrong to proceed to
address a new issue not yet in dispute; she can't tag on a list of
disputes that had not been put. The adjudicator's investigative
powers only permit contentions to be addressed that are an
integral part of the route to answering the ultimate question.
So what was it the adjudicator spotted? Karl and Sweeney
entered into a homemade subcontract invented by Karl. It did not
have the now unlawful pay-when-paid clause. Instead it had the
pay-when-certified clause. It said that although interim payments
became due, they were only payable when the value of the
equivalent works were included in the certificate from the
architect or contract administrator under the main contract or
otherwise approved by the employer under the contract. So, while
we had a become-due date that was clear, the final date for
payment was less certain.
The adjudicator, who by the way is one of the most experienced
and well respected in Scotland, took a look at that
pay-when-certified clause and asked if it complied with that part
of the Construction Act that requires contracts to "make
adequate provision" for determining what payments became due
and when. She announced that it was not compliant because it was
so uncertain about the payment day. Therefore she forked right on
the path and applied the Scheme for Construction Contracts'
payment rules to the question of when the money fell due. The
judge decided that the question was an ordinary and legitimate
part of the dispute. It did not trespass outside jurisdiction.
And what of the second point? It was said that the adjudicator
did not ask the parties to address her on this question. She took
the issue around the conference hall of her own mind and relied on
her one-woman debate. Karl was not happy with that approach, if it
is true. Had she come to them with her thoughts, they would have
hotly contested her thinking, they told the judge. Lord Caplan
said: "When a case is decided even provisionally, on a point
which parties may have had no opportunity to address, the court is
left feeling uncomfortable." Nevertheless he would not set
her decision aside. Karl must still pay up.
The uncomfortable feeling will arise in the mind of every
lawyer. If this had been litigation or arbitration, it would be an
error of procedure for the tribunal to put up and answer its own
questions without seeking observations from the parties. But
adjudication is not a fast-track species of an old idea. The
adjudicator is trusted to impartially investigate in any way she
sees fit unless the contract limits her activities. There is no
time for all the niceties of the legal system and some will
complain that the adjudicator here was unfair when compared with
traditional dispute resolution procedures. And am I uncomfortable?
Yes, I am.
Adjudication No 47: Karl
Construction (Scotland) Ltd vs Sweeney Civil Engineering Ltd
[21 December 2000] (Scottish Case).
Readers are invited to forward recent judgments for reporting
in this column (with full acknowledgement) to: Tony Bingham,
3 Paper Buildings, Temple, London EC4Y 7EU.
DX:007I LDE
Top
|